Overcoming Punjab’s Energy Crisis: A Case Study of the Financial Close of the Punjab Thermal Power Limited (PTPL) Project

Authors

  • Muhammad Aamir Jan National School of Public Policy, Lahore, Pakistan Author

Keywords:

energy, Punjab, finance, PTPL, Energy Crisis

Abstract

This case study explores the critical role played by the bureaucratic leadership of the Secretary of the Government of Punjab's Energy Department in driving the financial close of the 1263-megawatt Punjab Thermal Power Limited (PTPL) project valued at PKR 140 billion. The PTPL marked Pakistan's largest financing for a Re-gasified Liquefied Natural Gas (RLNG)-based power generation initiative with one of the world's highest designed efficiencies of 61.16%. The study demonstrates strategies adopted by the Secretary to overcome myriad challenges and bring this mega project's financing to fruition over a four-year period from 2018 to 2021. When assigned to lead the Energy Department in October 2018, the Secretary inherited the PTPL project in a catastrophic state. Construction had commenced hastily before fulfilling requirements like financial close, putting the provincial government's PKR 60 billion guarantees at risk of encashment. Lenders had abandoned the transaction due to unmet obligations. The case examines how the Secretary re-engaged stakeholders like lenders through consistent coordination, team motivation, and delegation based on capacity, and one-on-one relationship building. It analyzes his crisis management approach of prioritizing immediate targets like re-securing withdrawn lenders. The paper explores the bureaucratic leader's strategies for maintaining transparency and political ownership amidst disruptions like a change in regime and NAB investigations into power sector projects. It dissects the skills of the bureaucratic leaders in attracting new lenders by pitching the project as a secure investment given its 80% completion. The financing documents signed by six lending consortiums in early 2021 culminated in the celebrated financial close. The study derives key administrative and personal lessons on achieving mega project success via due diligence, political ownership, persistent policies, and continuity of tenure, prioritization, consultation, and negotiation skills. Recommendations based on this experience are provided for enhancing bureaucratic leadership effectiveness in future initiatives.

Downloads

Download data is not yet available.

References

Altshuler, A. & Luberoff, D. (2003). Mega-projects: The changing politics of urban public investment. The Brookings Institution.

De Bruin, L. (2020). Hersey and Blanchard Situational leadership Model: Adapting the leadership style to the follower. Business-to-you. https://www.business-to-you.com/hersey-blanchard-situational-leadership-model/

Hertogh, M., Baker, S., Staal-Ong, P. L., & Westerveld, E. (2008). Managing large infrastructure projects: Research on best practices and lessons learnt in large infrastructure projects in Europe. AT Osborne BV.

Luenendonk, M. (2020). Bureaucratic leadership guide: Definition, qualities, pros & cons, examples. Cleverism. https://cleverism.com/bureaucratic-leadership-guide/

Parth, F. R. (2014). Planning and controlling megaprojects. [Paper presentation] PMI® Global Congress 2014: North America, Phoenix, AZ. Newtown Square, PA: Project Management Institute.

Ritzer, G. (1993). The McDonaldization of society. California CA (Pine Forge Press).

Shenhar, A. & Holzmann. V. (2017). The three secrets of a megaproject success: Clear strategic vision, total alignment and adapting to complexity. Project Management Journal, 48 (6), 29-46. https://doi.org/10.1177/8756972817048006

Downloads

Published

2023-12-30

Issue

Section

Articles

How to Cite

Jan, M. A. (2023). Overcoming Punjab’s Energy Crisis: A Case Study of the Financial Close of the Punjab Thermal Power Limited (PTPL) Project. Journal of Pakistan Administration, 44(2), 1-21. https://journal.nspp.gov.pk/index.php/jpa/article/view/67